  "summary": "A fictional 1 MWp solar project can be studied at a 0.45 MW export limit today or 0.80 MW in two years. A separate one-day study tests what a battery could change.",
  "assumptions": [
    "1 MWp of solar and 0.80 MW of inverter capacity. The synthetic 8,760-hour profile produces 1,200 MWh before clipping in year one.",
    "Both solar cases use €600,000 of construction cost, €12,000 a year of operating cost, €80/MWh for exported energy and 0.5% annual generation degradation.",
    "NPV is measured today over the same 20 years, at 7% per year, in constant euros before debt and tax. The delayed case pays construction cost in year two and begins earning in year three. Both end in year twenty with zero terminal value."
  ],
  "cases": [
    {
      "id": "build-now",
      "label": "Build now",
      "description": "Build today and export at up to 0.45 MW throughout the study.",
      "first_operating_year_export_mwh": 1090.391,
      "npv_eur": 164062.92
    },
    {
      "id": "wait",
      "label": "Wait for more capacity",
      "description": "Defer construction by two years, then export at up to 0.80 MW.",
      "first_operating_year_export_mwh": 1200.0,
      "npv_eur": 186267.82
    }
  ],
  "battery_basis": "One synthetic summer day, with a 0.40 MW / 0.80 MWh AC battery, 5–95% state of charge and 90% round-trip efficiency. Both schedules begin and end at 5%. Hourly prices are assumed known for the day at €35/MWh before 07:00, €95/MWh from 18:00 to 22:00 and €55/MWh otherwise. Both export limits are 0.45 MW. Only the standalone case assumes a 0.40 MW import right. The day excludes auxiliary power, local demand, fees and ancillary services. Annual battery income and investment returns require a separate study.",
  "battery_cases": [
    {
      "id": "hybrid",
      "label": "Solar with a battery",
      "description": "A battery charges from solar that the export limit would curtail. The comparison is the same solar project operating alone.",
      "charge_mwh": 0.759,
      "discharge_mwh": 0.683,
      "grid_import_mwh": 0.0,
      "grid_export_mwh": 4.893,
      "curtailed_mwh": 0.334,
      "baseline_grid_export_mwh": 4.209,
      "baseline_curtailed_mwh": 1.093
    },
    {
      "id": "standalone",
      "label": "Standalone battery",
      "description": "A battery imports power to charge. The comparison is an empty connection with zero generation and zero exports.",
      "charge_mwh": 0.759,
      "discharge_mwh": 0.683,
      "grid_import_mwh": 0.759,
      "grid_export_mwh": 0.683,
      "curtailed_mwh": 0.0,
      "baseline_grid_export_mwh": 0.0,
      "baseline_curtailed_mwh": 0.0
    }
  ],
  "evidence": [
    "Obtain the signed grid agreement showing import and export rights separately, any restrictions, costs and the date of the proposed upgrade.",
    "Replace the illustrative yield and prices with a site design, a reviewed generation profile and market or offtake evidence.",
    "Confirm land rights, effective permits, delivery terms and project costs. For storage, obtain the supplier quote, warranty, auxiliary load and applicable grid charges."
  ],
  "provenance": [
    "PV8 planned-project assessment evaluated the two solar cash flows using the PV8 synthetic solar profile.",
    "PV8 battery dispatch solved each 24-hour schedule with the HiGHS optimiser. All prices, connection limits and equipment assumptions are illustrative."
  ]
}